Jasper Recreation Facilities Renovation Project

We know our facility is a little harder to navigate right now. Click here to download a helpful map.

Estimated Cost: $20.4 million

In 2019 the Municipality of Jasper secured $3,053,515 in provincial grant funding and $3,664,584 in federal grant funding towards a major renovation of the Activity Centre, Arena, and Fitness & Aquatics Centre facilities. Since August of 2021, administration has engaged a Project Management firm (WSP), a Prime Consultant (GEC Architecture), a Cost Consultant (DMC Cost Management) and a Construction Manager (Carlson Construction).

On February 22, 2022, Committee provided direction to administration on which design concepts should be further developed for Council’s consideration. On May 3, 2022, Council approved an expanded project scope and a total project budget of approximately $14 million. On September 27, 2022, Council approved the adjustment of the project scope to continue the design process with three (3) new arena dressing rooms and endorse the design concept of non-gendered change rooms in the aquatics centre.

On June 20, 2023, Council approved the increasing the Recreation Renovation Project budget by a total of $6.4M, to be funded by debenture. The cost increase is due to the impact of inflation since the project concept was originally developed.

The project willaddress significant lifecycle reinvestments in mechanical and electrical systems; improve physical accessibility and inclusion in a number of areas; fully renovate and modernize Aquatics Centre changing areas; fully renovate all existing Arena dressing rooms while adding an additional 3 new dressing rooms.

The Municipality of Jasper would like to express its gratitude to residents, business owners, and visitors for their patience and support as we undertake this transformative renovation project. We are confident that the enhanced Activity Centre will enrich the quality of life for all community members and contribute to a vibrant recreational environment in Jasper.


The Municipality of Jasper is committed to maintaining open lines of communication with residents, businesses, and stakeholders throughout the construction phase, and ensuring that access priorities are met to the best extent possible.
Regular updates on facility access, scheduling, and any necessary adjustments will be provided here.

Jasper Activity Centre Main Entrance Jasper Activity Centre Front Desk New Arena Dressing Room New Arena Hallways


At 6:00p.m. on Wednesday, the Arena dressing rooms and the main entrance on Bonhomme Street were officially open and ready for use.

Please note that the dressing rooms will require additional finishing touches in January. This work will be completed without any further closures.

Carlson Construction will be taking a short break over the holidays and will return in the new year to complete renovation work.  

Aquatic Centre & Changerooms Update:

The Aquatic Centre will open on December 26th. The hot tub opening will be delayed due to an emergency repair. We look forward to welcoming residents and visitors to the renewed facility over the holiday season. Check out the schedule here. 

Upcoming Closure Notice: 

Starting on January 6 or 7, 2025, renovations will begin on the back entrance of the Jasper Activity Centre, located across from Commemoration Park. This entrance will be closed for approximately 8 weeks as Carlson Construction installs new accessible doors and a full ramp to enhance accessibility.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week?

  • M&E finishes in Activity Centre
  • Final paint work in all areas 
  • Washroom fixtures in all areas 
  • Final door hardware finishes in all areas 
  • Final Clean in all areas 
  • All areas – electrical infrastructure (electricians work 24hrs)
  • Final inspections & Turnover 

Thank you for your continued patience as we navigate the renovation project.

Aquatic Centre Main PoolArena (New) Dressing RoomArena Dressing RoomArena Dressing Room ShowerArena Dressing Room WashroomsJasper Activity Centre Reception DeskMain Entrance on Bonhomme Street

Activity Centre:

To complete the switch to a new electrical panel, the Activity Centre will be closed from Saturday, December 14, at 6:00 PM to Monday, December 16, at 8:00 AM. This temporary closure is necessary to finalize key electrical upgrades that are part of the renovation.

The main entrance on Bonhomme Street and the lobby will re-open on Wednesday, December 18th.

Arena Update:

Arena dressing rooms will be ready for use on Wednesday, December 18th.

For more information on Arena schedule, please visit www.jasper-alberta.ca/p/arena

Aquatic Centre & Changerooms Update:

The Aquatic Centre will open on December 26th. The hot tub opening will be delayed due to an emergency repair. We look forward to welcoming residents and visitors to the renewed facility over the holiday season.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week?

  • M&E finishes in Activity Centre
  • Taping & painting in downstairs changeroom
  • Puck board finishes in Arena Hallway
  • Washroom fixtures in Arena
  • Dressing room accessories - Arena
  • Ongoing work in new electrical room
  • Column work in Aquatic Centre
  • Install railing & gates in Aquatic Centre
  • General cleaning, painting, installation of doors and hardware – All areas
  • All areas – electrical infrastructure (electricians work 24hrs)

Plans for Next Week:

  • M&E finishes in Activity Centre
  • Final paint work in all areas
  • Washroom fixtures in all areas
  • Final door hardware finishes in all areas
  • Final Clean in all areas
  • All areas – electrical infrastructure (electricians work 24hrs)
  • Final inspections & Turnover

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.


Arena Dressing RoomArena New CorridorCurling Lounge BarMain EntranceMain Lobby ElevatorMain Lobby into Main Entrance VestibuleMural Mural


Update #65 – December 6, 2024  

There will be a lot of activity in all areas of the renovation project over the next few weeks. All users can expect some construction happening when accessing the facilities the next few weeks.

Activity Centre:

To complete the switch to a new electrical panel, the Activity Centre will be closed from Saturday, December 14, at 6:00 PM to Monday, December 16, at 8:00 AM. This temporary closure is necessary to finalize key electrical upgrades that are part of the renovation.

As we move closer to completing the lobby area, the beautiful mural by local artist Jennifer Ottaway will be removed next week. We would like to thank Jennifer for her contribution, which made the space more welcoming and visually appealing. 

Arena Update:

Free public skating at various times on Sunday, December 8, between 10:00 AM and 6:00 PM. On Monday, December 9, Jasper Minor Sports will begin their practices in Jasper. Access to dressing room 5 will be available starting December 8, with the five new dressing rooms still on track to be ready for December 18.

Aquatic Centre & Changerooms Update:

The Aquatic Centre will open on December 26 and we look forward to welcoming residents and visitors to the renewed facility over the holiday season.

The repair work to the pool’s basin coating is completed. Over the next 3 weeks additional steps will be completed to ensure the facility meets safety and quality standards.

These include:

  • 10 days for the pool’s new paint to cure
  • 3–4 days to fill the pools
  • Two rounds of regulatory water testing, conducted at least one week apart
  • Staff recertification and testing

These steps are essential to providing a safe and enjoyable experience for all users. We appreciate your patience and understanding as we complete this critical work.  

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week?

  • Curling lounge final clean and turnover
  • Tiling in main floor lobby
  • Main floor ceiling in Activity Centre
  • Main entrance exterior painting 
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Painting scope in all areas of the Activity Centre
  • Ongoing puck board installation in Arena
  • Paining scope in Arena
  • Ongoing dressing room fixtures in Arena
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation
  • All areas – painting, installing doors and hardware, fire alarm verification

Plans for Next Week:

  • M&E finishes in Activity Centre
  • Taping & painting in downstairs changeroom
  • Puck board finishes in Arena Hallway
  • Washroom fixtures in Arena
  • Dressing room accessories - Arena
  • Ongoing work in new electrical room
  • Column work in Aquatic Centre
  • Install railing & gates in Aquatic Centre
  • General cleaning, painting, installation of doors and hardware – All areas
  • All areas – electrical infrastructure (electricians work 24hrs)

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

 

Arena Ice Existing Arena Dressing Room Arena Corridor Curling Lounge 


Arena Update: 

We are excited to announce that a soft opening for public skating is planned for December 8. Minor sports will also have ice time available during the week of December 9–12.

Access to dressing room 5 will be available starting December 8, with five new dressing rooms available starting December 18.  

Special thanks to our Arena Team for their hard work in getting the ice ready for opening! 

Aquatic Centre & Changerooms Update:

We’re excited to announce that the Aquatic Centre will open on December 26 and we look forward to welcoming residents and visitors to the renewed facility over the holiday season.

Work to repair the pool’s basin coating will be completed today, Friday, November 29th. Completing the pool basin coating now will eliminate the need for a regular maintenance shutdown in 2025.
 Over the next 3 weeks additional steps will be completed to ensure the facility meets safety and quality standards.

These include:

  • 10 days for the pool’s new paint to cure
  • 3–4 days to fill the pools
  • Two rounds of regulatory water testing, conducted at least one week apart
  • Staff recertification and testing

These steps are essential to providing a safe and enjoyable experience for all users. We appreciate your patience and understanding as we complete this critical work.   

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

 

What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Painting scope in all areas of the Activity Centre 
  • Demolition & Installation of T-Bar ceiling on main floor 
  • Ongoing puck board installation in Arena 
  • Ongoing dressing room benches in Arena 
  • Ongoing scope for the new electrical room in the Arena
  • Paining scope in Arena 
  • Ongoing dressing room fixtures in Arena 
  • Doors, hardware, & finishing touches in Curling Lounge 
  • Final clean in Curling Lounge 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

Plans for Next Week: 

  • Tiling in room 005
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Painting scope in all areas of the Activity Centre 
  • Ongoing puck board installation in Arena 
  • Ongoing dressing room benches in Arena 
  • Paining scope in Arena 
  • Ongoing dressing room fixtures in Arena 
  • Final clean in Curling Lounge 
  • Curling lounge turnover 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.





Arena Ice Flooding 

Mechanical Infrastructure Slide Pool BasinMain Pool Basin 
Arena Dressing Room Benches

Arena Users Update: 

  • Contractors arrived in Jasper Tuesday afternoon and started the ice plant, beginning the slab cooling process.
  • Our operators began flooding the surface today (Friday), a process that typically takes about 10 days to complete.
  • After the ice is finished, additional work will be done to ensure the arena is safe and ready for play, which may take up to a week. 
  • While ice making is underway, we will continue to complete the board and player-box improvement project.  

With the above timeline, we expect the arena ice will be ready for use the week of December 16th, with dressing rooms to follow. 

Delays in contractor availability have been a significant challenge, but we are doing everything possible to expedite this process while maintaining safety and quality standards. 


Aquatic Centre & Changerooms Update: 

Work to repair the pool’s basin coating began on Wednesday, November 13th and is ongoing. The projected opening date of the second week of December remains unchanged.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.


What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in all areas 
  • Insulation install in Activity Centre 
  • Millwork in Activity Centre main lobby 
  • Install automatic door in Fitness & Aquatics Centre 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories in Arena
  • Puck board installation in Arena 
  • Dressing room benches in Arena 
  • Doors, hardware, & finishing touches in Curling Lounge 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

 

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Painting scope in all areas of the Activity Centre 
  • Demolition & Installation of T-Bar ceiling on main floor 
  • Ongoing puck board installation in Arena 
  • Ongoing dressing room benches in Arena 
  • Ongoing scope for the new electrical room in the Arena
  • Paining scope in Arena 
  • Ongoing dressing room fixtures in Arena 
  • Doors, hardware, & finishing touches in Curling Lounge 
  • Final clean in Curling Lounge 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.


Arena Dressing Room Shower Arena Corridor Vinyl Composition Tiling in Activity Centre Basement Curling Lounge Bathroom Finishes 
Pool Basin Work


All timelines remain unchanged from last week.

Aquatic Centre & Changerooms Update
A contractor has been hired to repair the pool’s basin coating, and work began on Wednesday, November 13th. The projected opening date for the second week of December remains unchanged. 

Arena Update 

  • Carlson Construction continues to be on target to turn over all dressing rooms and off-ice areas to us by the third week of December. 
  • On November 1st, we successfully started up the ice plant and ice making has begun for the curling rink.  
  • The rink board and player box improvement project is ongoing. 
  • We expect to be able to begin ice making in the arena late next week as previously announced.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in all areas 
  • Drywalling in basement rooms at the Activity Centre 
  • Vinyl Composition Tiling (VCT) in basement lobby 
  • Installing countertops at main reception desk 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories in Arena
  • Installing the skate flooring in the Arena
  • Installation mirrors, doors, and hardware in curling lounge 
  • Canopy soffit framing in the plaza 
  • All areas – door frame install 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

  

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in all areas 
  • Insulation install in Activity Centre 
  • Millwork in Activity Centre main lobby 
  • Install automatic door in Fitness & Aquatics Centre 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories in Arena
  • Puck board installation in Arena 
  • Dressing room benches in Arena 
  • Doors, hardware, & finishing touches in Curling Lounge 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Arena Accessories Arena Corridor Arena Washroom PartitionsCurling Lounge Washroom Fixtures


Jasper Recreation Facilities Renovation Project Timeline: 

All timelines remain unchanged from last week.

1. Arena: 

  • Rink Board Modification: Projected for completion in early November.
  • Ice-Making Plant Start-up: November 1st.
  • Curling Ice: Projected second week of November.
  • Arena Ice: Projected third week of November.
  • Dressing Rooms: Projected third week of December. 

*Rink Board Modification: This project requires highly specialized skills and training, which made it difficult to secure the right contractors. Originally, a team of six employees from a contractor based in Hinton, was scheduled for the work in August. However, the wildfire and evacuation led to significant delays. Despite their other commitments, Quadra has gone above and beyond to adjust to our new timeline, working with a smaller crew of 2-3 as their availability allows. They have confirmed that there are no alternatives to accelerate the project further, as the work needs to be completed consecutively. The work is on track to be completed in time for us to clean the arena and begin ice-making by mid-November, which is the best outcome we could have hoped for given the circumstances.*  

2. Aquatic Centre & Changerooms:

  • Pool: Projected the second week of December.
    • Due to wildfire-related delays and the subsequent cleanup, the pool’s basin coating sustained damage. This coating is essential for safe and successful operation, so we are prioritizing immediate repairs. These repairs will add a 2 to 3 week delay to the previous projected date, pending contractor confirmation.
    • Projected dates are dependent on a successful start-up process, including filling the pool, testing for leaks, starting up mechanical systems, making any necessary repairs, and obtaining Public Health approval.
  • Changerooms: Projected the second week of November.

3. Curling Rink & Lounge:

  • Curling Rink: Projected second week of November.
  • Curling Lounge: Projected first week of December. 

4. Bonhomme Street:

  • Reopening: Projected for November 4th.
  • Roadwork: The road will be paved, and sidewalks will be completed.

5. Remainder of the Project:

  • Completion Date: Expected by the third week of December.
  • Key Areas:
    • Elevator
    • Main floor and basement lobbies
    • Downstairs accessible washroom
    • Main entrance plaza and doors

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week?
 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Drywalling in basement rooms at the Activity Centre 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories 
  • Installing the skate flooring in the Arena
  • Tiling & flooring scope in curling lounge 
  • Installation of sprinkler heads in curling lounge 
  • Canopy soffit framing in the plaza 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation
  • Bonhomme Street opened 

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Finishing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in all areas 
  • Drywalling in basement rooms at the Activity Centre 
  • Vinyl Composition Tiling (VCT) in basement lobby 
  • Installing countertops at main reception desk 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories in Arena
  • Installing the skate flooring in the Arena
  • Installation mirrors, doors, and hardware in curling lounge 
  • Canopy soffit framing in the plaza 
  • All areas – door frame install 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Arena Showers Bonhomme StreetCurling Lounge BarCurling Lounge Floor Wildflowers Childcare Fencing 


In last week’s update, we provided a revised project timeline. Please note that there has been a change in the projected timeline for the pool, outlined below. All other timelines remain unchanged.

Aquatic Centre & Changerooms:

  • Pool: Updated Opening Projection– Now anticipated for the second week of December.
    • Due to wildfire-related delays and the subsequent cleanup, the pool’s basin coating sustained damage. This coating is essential for safe and successful operation, so we are prioritizing immediate repairs. These repairs will add a 2 to 3 week delay to the previous projected date, pending contractor confirmation.
    • Projected dates are dependent on a successful start-up process, including filling the pool, testing for leaks, starting up mechanical systems, making any necessary repairs, and obtaining Public Health approval.
  • Changerooms: Updated Projection – Now expected to be ready by the second week of November.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.


What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Fire coating in the basement at Activity Centre 
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena
  • Tiling & flooring scope in curling lounge 
  • Millwork for bar area in curling lounge 
  • Installation of sprinkler heads in curling lounge 
  • Ongoing daycare fencing 
  • Aquatic Centre cleaning 
  • Asphalt installation on Bonhomme Street 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

 

Plans for Next Week:  

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Drywalling in basement rooms at the Activity Centre 
  • Ongoing scope for the new electrical room in the Arena
  • Washroom fixtures & dressing room accessories 
  • Installing the skate flooring in the Arena
  • Tiling & flooring scope in curling lounge 
  • Installation of sprinkler heads in curling lounge 
  • Canopy soffit framing in the plaza 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Arena Dressing Room WashroomExisting Arena Dressing Room Bonhomme Street Base Prep New Electrical Room 


Updated Jasper Recreation Facilities Renovation Project Timeline: 

1. Arena: 

  • Rink Board Modification: Projected for completion in early November.
  • Ice-Making Plant Start-up: November 1st.
  • Curling Ice: Projected second week of November.
  • Arena Ice: Projected third week of November.
  • Dressing Rooms: Projected third week of December.

*Rink Board Modification: This project requires highly specialized skills and training, which made it difficult to secure the right contractors. Originally, a team of six employees from a contractor based in Hinton, was scheduled for the work in August. However, the wildfire and evacuation led to significant delays. Despite their other commitments, Quadra has gone above and beyond to adjust to our new timeline, working with a smaller crew of 2-3 as their availability allows. They have confirmed that there are no alternatives to accelerate the project further, as the work needs to be completed consecutively. The work is on track to be completed in time for us to clean the arena and begin ice-making by mid-November, which is the best outcome we could have hoped for given the circumstances.* 

2. Aquatic Centre & Changerooms:

Pool: Projected third week of November. This is dependent on a successful start-up process, including filling the pool, checking for leaks, starting up mechanical systems, making any necessary repairs, and obtaining Public Health approval.

3. Curling Rink & Lounge:

  • Curling Rink: Projected second week of November.
  • Curling Lounge: Projected first week of December.

4. Bonhomme Street:

  • Reopening: Projected for November 4th.
  • Roadwork: The road will be paved, and sidewalks will be completed.

5. Remainder of the Project:

  • Completion Date: Expected by the third week of December.
  • Key Areas:
    • Elevator
    • Main floor and basement lobbies
    • Downstairs accessible washroom
    • Main entrance plaza and doors


If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Wall infills for the elevator doors on all floors in the Activity Centre
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena.
  • Ongoing fire stopping of all areas.
  • Door frame installations in all areas
  • Exterior curbs and sidewalks
  • Ongoing daycare fencing 
  • Exterior preparation work for asphalt installation 

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Fire coating in the basement at Activity Centre 
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena
  • Tiling & flooring scope in curling lounge 
  • Millwork for bar area in curling lounge 
  • Installation of sprinkler heads in curling lounge 
  • Ongoing daycare fencing 
  • Aquatic Centre cleaning 
  • Asphalt installation on Bonhomme Street 
  • All areas – electrical & fire alarm scope (electricians are working 24hrs to complete), ongoing fire stopping, ongoing door frame installation

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Bonhomme Street Sidewalk Daycare FencingDressing Room Test


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget, with the exception of any wildfire specific costs incurred. 

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Bonhomme Street Road Closure

Starting Monday, October 21st Bonhomme Street will be closed in front of the Jasper Activity Centre & Arena and Our Lady of Lourdes Catholic Church. The closure is anticipated to last until Monday, November 4th

The sidewalk on Bonhomme Street from Elm Street to the Fitness & Aquatic Centre, Museum, Catholic Church, and the parking lot/ recycling depot will remain open during the closure, as well as access from the parking lot to the Fitness & Aquatic Centre. Detour signage will be posted in the area, and the main parking lot and recycling centre will be accessible via the West entrance/exit.

This closure is necessary to accommodate gravel installation, compaction testing,  saw cutting, and laying asphalt. 

What Happened This Week? 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Wall infills for the elevator doors on all floors in the Activity Centre
  • Installing the ceiling grid in the curling lounge
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena
  • Ongoing fire stopping of all areas.
  • Door frame installations in all areas
  • Exterior curbs and sidewalks
  • Ongoing daycare fencing 

 

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Wall infills for the elevator doors on all floors in the Activity Centre
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena.
  • Ongoing fire stopping of all areas.
  • Door frame installations in all areas
  • Exterior curbs and sidewalks
  • Ongoing daycare fencing 
  • Exterior preparation work for asphalt installation 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.


Aquatic Centre Changeroom TestNew Dressing Room in Existing Arena Arena Skate FlooringNew Sidewalks on Bonhomme Street


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget, with the exception of any wildfire specific costs incurred. 

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Aquatic Centre Update: 

Contractors hired by our insurance company are actively working on cleaning and remediation in the Aquatic Centre, which includes scaffolding that is set up to reach high areas. The timeline for this work to be complete is uncertain at this time. 

Once we gain access to the pool, our team at the Fitness & Aquatic Centre will need approximately three weeks to complete the necessary work, including filling and testing the pool. 

If any unforeseen damage is discovered, such as from the scaffolding itself, this could extend the timeline further. While we are hopeful for a reopening date in 2024, this will depend on how these factors unfold. We understand the importance of the Aquatic Centre, and will continue to prioritize its opening, and provide updates when we have them.  

What Happened This Week?

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Wall infills for the elevator doors on all floors in the Activity Centre
  • Installing the ceiling grid in the curling lounge
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena
  • Ongoing fire stopping of all areas.
  • Door frame installations in all areas
  • Exterior curbs and sidewalks

Plans for Next Week: 

  • Taping (for drywall) all areas in the Activity Centre
  • Ongoing mechanical and electrical rough-ins in the Activity Centre
  • Ongoing work for the new electrical infrastructure in the Activity Centre
  • Paint scope in the Activity Centre
  • Wall infills for the elevator doors on all floors in the Activity Centre
  • Drywalling and taping in the Arena
  • Ongoing mechanical and electrical rough-ins in the Arena
  • Ongoing scope for the new electrical room in the Arena
  • Tiling and painting scope in the Arena
  • Installing the skate flooring in the Arena.
  • Ongoing fire stopping of all areas.
  • Door frame installations in all areas
  • Exterior curbs and sidewalks

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

 

Arena Door FramesArena Dressing RoomRoad Access to ArenaTiles in Arena Showers


𝐉𝐚𝐬𝐩𝐞𝐫 𝐑𝐞𝐜𝐫𝐞𝐚𝐭𝐢𝐨𝐧 𝐅𝐚𝐜𝐢𝐥𝐢𝐭𝐢𝐞𝐬 𝐑𝐞𝐧𝐨𝐯𝐚𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐖𝐞𝐞𝐤𝐥𝐲 𝐔𝐩𝐝𝐚𝐭𝐞:
The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget, with the exception of any wildfire specific costs incurred.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐖𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤?
◾ Taping (for drywall) all areas in the Activity Centre
◾ Ongoing mechanical and electrical rough-ins in the Activity Centre
◾ Ongoing work for the new electrical infrastructure in the Activity Centre
◾ Paint scope in the Activity Centre
◾ Wall infills for the elevator doors on all floors in the Activity Centre
◾ Installing the ceiling grid in the curling lounge
◾ Final finishes in the Aquatic Centre
◾ Drywalling and taping in the Arena
◾ Ongoing mechanical and electrical rough-ins in the Arena
◾ Ongoing scope for the new electrical room in the Arena
◾ Tiling and painting scope in the Arena
◾ Ongoing fire stopping of all areas.
◾ Door frame installations in all areas
◾ Prep work for curbs and sidewalks

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:
◾ Taping (for drywall) all areas in the Activity Centre
◾ Ongoing mechanical and electrical rough-ins in the Activity Centre
◾ Ongoing work for the new electrical infrastructure in the Activity Centre
◾ Paint scope in the Activity Centre
◾ Wall infills for the elevator doors on all floors in the Activity Centre
◾ Installing the ceiling grid in the curling lounge
◾ Final finishes in the Aquatic Centre
◾ Drywalling and taping in the Arena
◾ Ongoing mechanical and electrical rough-ins in the Arena
◾ Ongoing scope for the new electrical room in the Arena
◾ Tiling and painting scope in the Arena
◾ Installing the skate flooring in the Arena.
◾ Ongoing fire stopping of all areas.
◾ Door frame installations in all areas
◾ Exterior curbs and sidewalks

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Aquatic PartitionsPlaza SlabTiling Scope in ArenaSafety Test


𝐉𝐚𝐬𝐩𝐞𝐫 𝐑𝐞𝐜𝐫𝐞𝐚𝐭𝐢𝐨𝐧 𝐅𝐚𝐜𝐢𝐥𝐢𝐭𝐢𝐞𝐬 𝐑𝐞𝐧𝐨𝐯𝐚𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐖𝐞𝐞𝐤𝐥𝐲 𝐔𝐩𝐝𝐚𝐭𝐞:
The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget, with the exception of any wildfire specific costs incurred.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐖𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤?
◾ Placed and finished the Plaza slab in front of the Activity Centre
◾ Safety tested and Director approved Plaza slab
◾ Continued work on electrical infrastructure in the Activity Centre
◾ Began installing the partitions in the Aquatic Centre
◾ Restarted the tiling scope for the Arena

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:
◾ Taping (for drywall) all areas in the Activity Centre
◾ Ongoing mechanical and electrical rough-ins in the Activity Centre
◾ Ongoing work for the new electrical infrastructure in the Activity Centre
◾ Paint scope in the Activity Centre
◾ Activity Centre re-opening to residents on Tuesday, October 1 at 10:00AM
◾ Wall infills for the elevator doors on all floors in the Activity Centre
◾ Installing the ceiling grid in the curling lounge
◾ Final finishes in the Aquatic Centre
◾ Drywalling and taping in the Arena
◾ Ongoing mechanical and electrical rough-ins in the Arena
◾ Ongoing scope for the new electrical room in the Arena
◾ Tiling and painting scope in the Arena
◾ Ongoing fire stopping of all areas.
◾ Door frame installations in all areas
◾ Beginning prep work for curbs and sidewalks

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside!!

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Scaffolding in Aquatic CentreAquatic Centre PartitionsPlaza Slab Rebar Install

𝐉𝐚𝐬𝐩𝐞𝐫 𝐑𝐞𝐜𝐫𝐞𝐚𝐭𝐢𝐨𝐧 𝐅𝐚𝐜𝐢𝐥𝐢𝐭𝐢𝐞𝐬 𝐑𝐞𝐧𝐨𝐯𝐚𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐖𝐞𝐞𝐤𝐥𝐲 𝐔𝐩𝐝𝐚𝐭𝐞:
The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget, with the exception of any wildfire specific costs incurred.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐇𝐞𝐫𝐞'𝐬 𝐰𝐡𝐚𝐭'𝐬 𝐛𝐞𝐞𝐧 𝐡𝐚𝐩𝐩𝐞𝐧𝐢𝐧𝐠: 

  • Carlson has been back onsite since September 5th prepping for the Plaza Slab pour which is scheduled for this weekend (20th & 21st)
  • Aquatic washroom/change room partitions were delivered on September 18th and install has started. 

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Full construction of all areas to start the week of September 30th to push this project across the finish line.
  • Fitness centre opening on Monday, September 23rd.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and partial access to changerooms, with bathrooms inside!!

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

Plaza gravel base for new concrete slabOngoing curling lounge scopeAccessible doors into fully accessible washrooms/shower roomsMain floor security grill track for new reception deskNew access ramp to changing areas in Aquatic CentreArena corridor windows


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Taping in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing demolition of the ceiling in the curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Wall infills for the elevator doors in the Activity Centre.
  • Installation of security grill track (the grill that will go around the new front desk area when not in use) supports in the Activity Centre.
  • Painting scope in the Activity Centre.
  • Installing doors and hardware (auto-operators) in the Aquatic Centre.
  • Final inspections in the Aquatic Centre.
  • Mechanical start-ups in the Aquatic Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Painting in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing mechanical and electrical rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Drywall scope for the Arena. 
  • Tiling scope into the Arena.
  • Ongoing fire stopping in all areas. 
  • Exterior site subgrade preparation.  

Plans for next week:

  • Taping in all areas of the Activity Centre.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Installation of the ceiling grid in the curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Painting scope in the Activity Centre.
  • Wall infills for the elevator doors on all floors in the Activity Centre.
  • Final finishes in the Aquatic Centre.
  • Final cleaning in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical rough-ins in the Arena extension.
  • Drywalling & taping in the Arena.
  • Tiling scope in the Arena. 
  • Painting scope for the Arena.
  • Ongoing fire stopping of all areas.
  • Exterior site base prep and rebar placement.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project

 


Aquatic Adult Lift Station

Aquatic South Area (previously male changing area)Curling Lounge (elevator door & bar area)Subgrade Prep (plaza concrete slab)

Elevator Lobby (basement)

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Taping in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Demolition of the ceiling in the curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Wall infills for the elevator doors in the Activity Centre.
  • Painting scope in the Activity Centre.
  • Painting in the Aquatic Centre.
  • Installing washroom fixtures and accessories in the Aquatic Centre.
  • Finishing the mechanical & electrical rough-ins in the Aquatic Centre.
  • Final inspections in the Aquatic Centre.
  • Mechanical start-ups in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing mechanical and electrical rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Ongoing tiling scope into the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Exterior site subgrade preparation.  

Plans for next week:

  • Ongoing taping in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Installation of the ceiling grid in the curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Painting scope in the Activity Centre.
  • Wall infills for the elevator doors in the Activity Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Cleaning in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical rough-ins in the Arena extension.
  • Ongoing tiling scope in the Arena. 
  • Painting scope for the Arena.
  • Ongoing fire stopping of all areas.
  • Exterior site subgrade preparation.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project

 

Aquatic lockers
Aquatic washroom finishesArena corridor framingArena tiling scopeSite subgrade prep for concrete


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Drywalling and taping in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Installation of the elevator shaft envelope in the Activity Centre.
  • Installation of the elevator in the Activity Centre.
  • Painting in the Aquatic Centre.
  • Installing washroom fixtures and accessories in the Aquatic Centre.
  • Finishing the mechanical & electrical rough-ins in the Aquatic Centre.
  • Final inspections in the Aquatic Centre.
  • Mechanical start-ups in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Starting tiling scope into the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Exterior site subgrade preparation.  

Plans for next week:

  • Ongoing installation of drywall and taping in the curling lounge
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Installation of the elevator shaft envelope in the Activity Centre.
  • Wall infills for the elevator doors in the Activity Centre.
  • Ongoing installation of washroom fixtures and accessories for the Aquatic Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Cleaning in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension.
  • Tiling scope in the Arena. 
  • Painting scope for the Arena.
  • Ongoing fire stopping of all areas.
  • Exterior site subgrade preparation.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project

 

Activity Centre Second Floor Elevator DoorAquatic Centre CabanaAquatic Centre Accessible RampAquatic Centre Common Area Vanities


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Drywalling and taping in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Installation of the elevator shaft envelope in the Activity Centre.
  • Installation of the elevator in the Activity Centre.
  • Installation of the lockers in the Aquatic Centre.
  • Painting in the Aquatic Centre.
  • Installing washroom fixtures and accessories in the Aquatic Centre.
  • Finishing the mechanical & electrical rough-ins in the Aquatic Centre.
  • Starting final inspections in the Aquatic Centre.
  • Mechanical start-ups in the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Starting tiling scope into the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Exterior site subgrade preparation.  

Plans for next week:

  • Ongoing installation of drywall and taping in the curling lounge
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing work for the new electrical infrastructure in the Activity Centre.
  • Installation of the exterior envelope (vapour barrier and insulation) for elevator shaft. 
  • Installation of the elevator in the Activity Centre.
  • Ongoing installation of washroom fixtures and accessories for the Aquatic Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Painting in the Aquatic Centre.
  • Final inspections in the Aquatic Centre. 
  • Mechanical start-ups in the Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension.
  • Tiling scope in the Arena. 
  • Painting scope for the Arena.
  • Ongoing fire stopping of all areas.
  • Exterior site subgrade preparation.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


Accessible shower
Elevator StagingVanities in Common AreaWashroom

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Installing drywall in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing prep work for the new electrical infrastructure in the Activity Centre.
  • Installation of the elevator in the Activity Centre.
  • Installation of security grill (the grill that will go around the new front desk area when not in use) supports in the Activity Centre.
  • Painting scope for the Aquatic Centre.
  • Installing washroom fixtures and accessories in the Aquatic Centre.
  • Installation of a block wall in the Aquatic Centre.
  • Tiling in the Aquatic Centre.
  • Installation of the exterior envelope (vapour barrier and insulation) for the Arena. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Painting scope for the Arena.
  • Preparation for tiling scope into the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Pathway closure and fence removal for the Daycare.

Plans for next week:

  • Ongoing installation of drywall and taping in the curling lounge
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing prep work for the new electrical infrastructure in the Activity Centre.
  • Installation of the exterior envelope (vapour barrier and insulation) for elevator shaft. 
  • Installation of the elevator in the Activity Centre.
  • Ongoing installation of washroom fixtures and accessories for the Aquatic Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Painting in the Aquatic Centre.
  • Beginning final inspections in the Aquatic Centre. 
  • Mechanical start-ups in the Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension.
  • Tiling scope in the Arena. 
  • Painting scope for the Arena.
  • Ongoing fire stopping of all areas.
  • Exterior site subgrade preparation.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

 

 


Arena CorridorAquatic FixturesPainting in the Aquatic CentreCurling Lounge Washrooms


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Installing drywall in the curling lounge.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing prep work for the new electrical infrastructure in the Activity Centre.
  • ATCO installation of a transformer for the Aquatic Centre.
  • Painting scope for the Aquatic Centre.
  • Installing washroom fixtures and accessories in the Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Painting scope for the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Plans for next week:

  • Ongoing installation of drywall and taping in the curling lounge
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing prep work for the new electrical infrastructure in the Activity Centre.
  • Installation of the exterior envelope (vapour barrier and insulation) for elevator shaft. 
  • Installation of the elevator in the Activity Centre.
  • Installation of security grill (the grill that will go around the new front desk area when not in use) supports in the Activity Centre.
  • Ongoing installation of washroom fixtures and accessories for the Aquatic Centre.
  • Finishing the mechanical and electrical ceiling rough-ins in the Aquatic Centre.
  • Installation of a block wall in the Aquatic Centre.
  • Painting scope for the Aquatic Centre.
  • Tiling scope for Arena extension.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Installation of door frames in the Arena.
  • Painting scope for the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Exterior site work: Removal of the access path for the Daycare from Bonhomme Street (Saturday, June 22nd)

 

The reopening of the Aquatic Centre, initially expected at the end of June, will be delayed due to unforeseen supply chain issues with the partition panels for changing spaces and showers. These panels are now expected to arrive in mid-August. 

We understand the frustration and disappointment this delay may cause for our community members eagerly awaiting the reopening of the aquatic centre.

The Municipality is actively working with our suppliers and construction partners to expedite the process and explore all possible solutions to proceed sooner and open the facility by the end of July. Overall, the whole renovation project is still expected to be completed in Q3. 

We are also working with the project team to explore creative ways that may allow us to provide some level of service to the community during this additional short delay.

In the meantime, we are taking advantage of the downtime to perform necessary maintenance, such as replacing pool tank expansion joint gaskets and removing flaking paint from ducting in the pool area. We will continue to provide regular updates every Friday and we thank Jasperites for their understanding and patience.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


Curling Lounge Framing (new bar area)

Elevator Shaft

Painting Scope Into New arena Dressing Rooms

New Plaza Canopy Roof


The Fitness Centre will be CLOSED starting June 8th for one week. This temporary closure is part of the Jasper Recreation Facilities Renovation Project and is necessary to accommodate the following upgrades and improvements:

Painting: Walls and ceilings will be painted throughout the week with epoxy, which requires 48 hours to ensure any odors dissipate.

Power Upgrade: An essential ATCO power upgrade will be conducted to enhance our facilities.

We apologize for any inconvenience this may cause and appreciate your cooperation and understanding.

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Ongoing installation of roofing around elevator shaft and plaza canopy.
  • Removal of hoarding around the elevator shaft.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Installing the pool deck lighting in the Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Painting scope for the Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Painting scope for the Arena.
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Plans for next week:

  • Installing drywall in the curling lounge
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing prep work for the new electrical infrastructure in the Activity Centre.
  • ATCO installation of a transformer for the Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Painting scope for the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


Aquatic Breezeway between Fitness and Pool Deck

New Arena CorridorPlaza Canopy Re-Roof




The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Installation of roofing around elevator shaft.
  • Plaza roof demolition and re-roofing.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Installing the pool deck lighting in the Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Plans for next week:

  • Elevator shaft and plaza canopy roofing. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope into the existing mechanical room in the Fitness & Aquatic Centre.
  • Ongoing installation of pool deck lighting.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Painting scope for the Aquatic Centre.
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Painting scope for the Arena.
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s What Happened This Week:

  • Installation of roofing around elevator shaft.
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena.  
  • Weekend work in the ceiling space of Wildflowers Childcare Centre.

Plans for next week:

  • Elevator shaft preparation for roofing. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Ongoing scope for new electrical room in the Arena extension.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s What Happened This Week:

  • Ongoing elevator shaft wall installation. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Installation of block walls for the new electrical room in the Arena.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena.  

 

Plans for next week:

  • Elevator shaft preparation for roofing. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Starting painting in Arena.  
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena.  
  • Weekend ceiling work in Wildflowers Childcare Centre.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here’s what happened this week:

  • Framing and boarding the elevator shaft walls in the Activity Centre
  • Ongoing mechanical & electrical rough-ins in curling lounge
  • Ongoing dry-packing floor elevations & waterproofing in Aquatic Centre changerooms. 
  • Start the tiling in the Aquatic Centre changerooms.
  • Mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre. 
  • Electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Place & finish concrete slab infills in new Arena electrical room. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena. 

Plans for next week:

  • Ongoing elevator shaft wall installation. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Steel stud framing in the curling lounge.
  • Ongoing tiling & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Ongoing electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Installation of block walls for the new electrical room in the Arena.
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena.  

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s What Happened This Week:

  • Starting slab infills around the elevator shaft in the Activity Centre
  • Starting the wall layouts for the curling lounge in the Activity Centre 
  • Installation of the coring slab for the mechanical in the curling lounge. 
  • Ongoing ceiling & drywall taping in Fitness & Aquatic Centre changerooms. 
  • Ongoing dry-packing & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre. 
  • Electrical scope into the main distribution panel in the Fitness & Aquatic Centre. 
  • Start demolition in the area for the new electrical room in the Arena. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in existing dressing room area. 
  • Ongoing fire stopping in Arena and Aquatic Centre. 
  • Ongoing installation of exterior cladding on Arena. 
  • Installation of hydrant. 

Plans for next week:

  • Elevator shaft wall installation. 
  • Ongoing mechanical & electrical rough-ins in curling lounge. 
  • Ongoing dry-packing & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
  • Starting tiling work in Aquatic Centre. 
  • Ongoing exterior envelope & cladding on Arena extension. 
  • Prep work for concrete slab infills in new Arena electrical room. 
  • Mechanical & electrical rough-ins in Arena. 
  • Ongoing installation of block walls in existing Arena dressing rooms. 
  • Ongoing fire stopping work in Arena & Aquatic Centre. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

 

𝐉𝐚𝐬𝐩𝐞𝐫 𝐑𝐞𝐜𝐫𝐞𝐚𝐭𝐢𝐨𝐧 𝐅𝐚𝐜𝐢𝐥𝐢𝐭𝐢𝐞𝐬 𝐑𝐞𝐧𝐨𝐯𝐚𝐭𝐢𝐨𝐧 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐖𝐞𝐞𝐤𝐥𝐲 𝐔𝐩𝐝𝐚𝐭𝐞:

Beginning Monday, April 29, Bonhomme Street will be closed in front of the Jasper Activity Centre & Arena and Our Lady of Lourdes Catholic Church. 

The sidewalk on Bonhomme Street from Elm Street to the Fitness & Aquatic Centre, Museum, Catholic Church, and the parking lot/ recycling depot will remain open during the closure, as well as access from the parking lot to the Fitness & Aquatic Centre. 

Detour signage will be posted in the area, and the main parking lot and recycling centre will be accessible via the West entrance/exit.

This closure is necessary to accommodate hydrant installation work, and is anticipated to last until May 2nd.
We apologize for the inconvenience and thank you for your cooperation.
 The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:
• Finishing the installation of the main steel for the elevator in the Activity Centre
• Starting demolition of the curling lounge in the Activity Centre.
• Installing locker bases in the Aquatic Centre.
• Ongoing ceiling & drywall taping in Fitness & Aquatic Centre changerooms.
• Starting dry-packing & waterproofing in Fitness & Aquatic Centre changerooms.
• Ongoing mechanical & electrical work in existing arena.
• Finishing block walls in the Arena extension.
• Starting block walls in existing dressing rooms in the Arena.
• Fire stopping in Arena and Aquatic Centre.
 • Installing exterior cladding on Arena.

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:
• Starting slab infills around the elevator shaft in the Activity Centre
• Starting installation of the elevator shaft walls.
• Starting the wall layouts for the curling lounge in the Activity Centre
• Installation of the coring slab for the mechanical in the curling lounge.
• Ongoing ceiling & drywall taping in Fitness & Aquatic Centre changerooms.
• Ongoing dry-packing & waterproofing in Fitness & Aquatic Centre changerooms.
• Mechanical scope (tying the new mechanical system) into the existing mechanical room in the Fitness & Aquatic Centre.
• Electrical scope into the main distribution panel in the Fitness & Aquatic Centre.
• Start demolition in the area for the new electrical room in the Arena.
• Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension.
• Ongoing installation of block walls in existing dressing room area.
• Ongoing fire stopping in Arena and Aquatic Centre.
• Ongoing installation of exterior cladding on Arena.
 • Installation of the area’s fire hydrant.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s What Happened This Week:

  • Ongoing installation of the main steel for the elevator in the Activity Centre.
  • Ongoing installation of ceiling drywall in Aquatic Centre.
  • Installation of lighting fixtures in Aquatic Centre. 
  • Starting the dry packing for shower floor elevations in Aquatic Centre. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Finishing block walls in the Arena extension.
  • Starting block walls in existing dressing room area. 
  • Fire stopping in Arena and Aquatic Centre. 
  • Installing exterior cladding on Arena. 

 

Plans for next week: 

  • Ongoing installation of  block walls in existing area.
  • Ongoing mechanical & electrical work in existing arena. 
  • Ongoing exterior envelope & cladding. 
  • Ongoing ceiling & drywall taping in Fitness & Aquatic Centre changerooms. 
  • Starting dry-packing & waterproofing in Fitness & Aquatic Centre changerooms. 
  • Ongoing mechanical & electrical work in Fitness & Aquatic Centre changerooms. 
  • Coring (concrete drilling) scope for mechanical & electrical work in Curling Lounge. 
  • Start exterior elevator shaft work. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.  

Here’s what happened this week: 

  • Installation of the main steel for the elevator in the Activity Centre.
  • Installation of ceiling drywall in Aquatic Centre.
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre.
  • Installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in Arena extension.
  • Wall layout for existing dressing room area.
  • Installation of the Heat Recovery Ventilation (HRV) unit on the Arena roof.
  • Ongoing installation of exterior wall membrane on Arena.

Plans for next week:

  • Ongoing installation of the main steel for the elevator in the Activity Centre.
  • Ongoing installation of ceiling drywall in Aquatic Centre.
  • Installation of lighting fixtures in Aquatic Centre. 
  • Starting the dry packing for shower floor elevations in Aquatic Centre. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Finishing block walls in the Arena extension.
  • Starting block walls in existing dressing room area. 
  • Fire stopping in Arena and Aquatic Centre. 
  • Installing exterior cladding on Arena. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

The Fitness & Aquatic Centre will be CLOSED for three days (April 11, 12, & 13) to accommodate planned electrical work as part of the Jasper Recreation Facilities Renovation Project. The Activity Centre & Arena will remain open. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Ongoing installation of the main steel for the elevator in the Activity Centre.
  • Ongoing installation of ceiling framing in Aquatic Centre.
  • Ongoing installation of backer board perimeter walls for the Aquatic Centre. *backer board is a building material made from cement and fiberglass mesh
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in Arena extension.
  • Ongoing work on existing dressing room bulkheads and final grade for slab.
  • Ongoing installation of exterior wall membrane on Arena.
  • Place & finish concrete slab in Arena. 
  • Installation of rebar in Arena. 

Plans for next week:

  • Ongoing installation of the main steel for the elevator in the Activity Centre.
  • Installation of ceiling drywall in Aquatic Centre.
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in Arena extension.
  • Wall layout in existing Arena dressing rooms. 
  • Installation of HRV (heat recovery ventilator) unit on Arena roof. 
  • Ongoing installation of exterior wall membrane on Arena.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.  

Here’s what happened this week: 

  • Installation of the main steel for the elevator in the Activity Centre.
  • Installation of ceiling framing in Aquatic Centre.
  • Installation of backer board perimeter walls for the Aquatic Centre. *backer board is a building material made from cement and fiberglass mesh
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre.
  • Ongoing roof assembly on the Arena extension.
  • Installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Installation of radon rock for new hallway area in the Arena.
  • Installation of block walls in the new Arena extension.
  • Block infills for new doorway openings.
  • Work on existing dressing room bulkheads and final grade for slab.
  • Installation of exterior wall membrane on Arena.

 

Plans for next week:

  • Ongoing installation of the main steel for the elevator in the Activity Centre.
  • Ongoing installation of ceiling framing in Aquatic Centre.
  • Ongoing installation of backer board perimeter walls for the Aquatic Centre. *backer board is a building material made from cement and fiberglass mesh
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre. 
  • Ongoing installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Ongoing installation of block walls in Arena extension.
  • Ongoing work on existing dressing room bulkheads and final grade for slab.
  • Ongoing installation of exterior wall membrane on Arena.
  • Place & finish concrete slab in Arena. 
  • Installation of rebar in Arena. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

  • Installation of main steel for elevator in the Activity Centre.
  • Installation of mechanical and electric ceiling rough-ins in the Aquatic Centre. 
  • Installation of ceiling framing in the Aquatic Centre.
  • Installation of backer board perimeter walls for the Aquatic Centre.
  • Ongoing roof assembly on the Arena extension.
  • Installation of mechanical and electrical ceiling rough-ins in the new Arena extension.
  • Installation of block walls in the new Arena extension.
  • Block infills for new doorway openings in existing Arena.
  • Subgrade preparation for the new hallway area in Arena.
  • Installation of exterior wall membrane on Arena.

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Installation of the main steel for the elevator in the Activity Centre.
  • Installation of ceiling framing in Aquatic Centre.
  • Installation of backer board perimeter walls for the Aquatic Centre.
  • Ongoing installation of mechanical and electric ceiling rough-ins in the Aquatic Centre.
  • Ongoing roof assembly on the Arena extension.
  • Installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Installation of radon rock for new hallway area in the Arena.
  • Installation of block walls in the new Arena extension.
  • Block infills for new doorway openings.
  • Work on existing dressing room bulkheads and final grade for slab.
  • Installation of exterior wall membrane on Arena.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project.


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

  • Installation of mechanical and electrical ceiling rough-ins in the new Arena extension.
  • Preparation work for rebar installation in the existing Arena dressing rooms.
  • Ongoing roof assembly on the Arena extension.
  • Installing parapets in Arena extension.
  • Installation of perimeter fire-rated walls in the Aquatic Centre.
  • Installing block walls in the Aquatic Centre.
  • Relocating electrical lines for the Activity Centre elevator.
  • Installation of mechanical and electric ceiling rough-ins in the Aquatic Centre. 
  • Relocating data and fire alarm wiring as well as sprinkler lines in the Activity Centre.
  • Demolition of the wall in the curling lounge.
  • Abatement process for the elevator area in Activity Centre.

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Installation of the main steel for the elevator in the Activity Centre.
  • Ongoing installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 
  • Installation of ceiling framing in Aquatic Centre.
  • Ongoing roof assembly on the Arena extension.
  • Installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Installation of radon rock for new hallway area in the Arena.
  • Ongoing roof assembly work on Arena extension.
  • Installation of block walls in the new Arena extension.
  • Block infills for new doorway openings.
  • Work on existing dressing room bulkheads.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project.


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

  • Installation of mechanical and electrical ceiling rough-ins in the new Arena extension.
  • Installing block walls in the new Arena extension.
  • Preparation work for rebar installation in the existing Arena dressing rooms.
  • Starting roof assembly on the Arena extension.
  • Installing parapets on Arena extension.
  • Installation of perimeter fire-rated walls in Aquatic Centre.
  • Installing block walls in the Aquatic Centre.
  • Relocating electrical lines for Activity Centre elevator.
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 
  • Installation of temporary roof hoarding (temporary walls) for the Activity Centre elevator.
  • Relocating data wiring in the Activity Centre
  • Abatement process for the elevator area in Activity Centre.

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Preparation work for elevator steel installation
  • Ongoing installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 
  • Ongoing installation of perimeter fire-rated walls in Aquatic Centre.
  • Roof assembly on the Arena extension.
  • Installation of mechanical and electrical ceiling rough-ins in the Arena extension. 
  • Installation of radon rock for new hallway area in the Arena.
  • Ongoing roof assembly work on Arena extension.
  • Layout for block walls in the new Arena extension 
  • Construction of new doorways constructed in the existing Arena wall from the existing dressing rooms to access the new corridor.
  • Work on existing dressing room bulkheads

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project.

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

 If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

  • Placed and finished concrete slab in new Arena extension.
  • Preparation of subgrade for the new hallway area.
  • Installing parapets on Arena extension.
  • Installing block walls in the Aquatic Centre.
  • Relocating electrical lines for Activity Centre elevator.
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Place & finish concrete slab in new Arena extension.
  • Ongoing preparation work for rebar installation in the existing Arena dressing rooms.
  • Ongoing preparation of subgrade and radon rock for new hallway area in the Arena.
  • Ongoing parapet installation on Arena extension.
  • Ongoing roof assembly work on Arena extension.
  • Ongoing installation of block walls in Aquatic Centre.
  • Installation of perimeter fire-rated walls in Aquatic Centre.
  • Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre. 
  • Ongoing relocation of sprinklers, electrical lines, and HVac ducts in Activity Centre for elevator. 
  • Installation of temporary roof hoarding (temporary walls) and elevator shoring.
  • Starting abatement process for the elevator area in Activity Centre.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project.


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.  

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Preparing for rebar installation in the existing Arena dressing rooms. 
  • Preparation of subgrade for the new hallway area. 
  • Installing parapets on Arena extension. 
  • Starting the roof assembly on the Arena. 
  • Installing block walls in the Aquatic Centre. 
  • Relocating sprinklers and electrical lines for Activity Centre elevator. 
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 

 

Plans for next week: 

  • Place & finish concrete slab in new Arena extension. 
  • Ongoing preparation work for rebar installation in the existing Arena dressing rooms. 
  • Ongoing preparation of subgrade for new hallway area in the Arena. 
  • Ongoing parapet installation on Arena extension. 
  • Ongoing roof assembly work on Arena extension. 
  • Ongoing installation of block walls on Arena extension. 
  • Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre. 
  • Ongoing relocation of sprinklers, electrical lines, and HVac ducts in Activity Centre for elevator. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 


 

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here's what happened this week:

  • Installing parapets on Arena
  • Installing radon system in the new Arena extension area
  • Preparation for rebar installation in existing dressing rooms
  • Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre
  • Installing block walls in Aquatic Centre
  • Relocating sprinklers and electrical lines for Activity Centre elevator.

Plans for next week:

  • Preparing for rebar installation in the existing dressing rooms
  • Preparation of subgrade for the new hallway area
  • Installing parapets on Arena extension
  • Starting the roof assembly on the Arena
  • Installing block walls in the Aquatic Centre
  • Relocating sprinklers and electrical lines for Activity Centre elevator
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available.

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.

Here's what happened this week:

  • Installing curtain wall window frames and parapets on Arena extension
  • Block wall in-fills on Arena extension
  • Back filling and subgrade preparation for concrete slab in Arena extension
  • Subgrade preparation for concrete slab in existing Arena dressing rooms.
  • Installation of fire-rated ceilings and miscellaneous framing work in Aquatic Centre.
  • Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre.
  • Set up masonry “mud shack” for work in Aquatic Centre.

Plans for next week:

  • Installing radon system for Arena extension.
  • Installing parapets on Arena extension.
  • Relocating sprinklers and electrical lines for Activity Centre elevator.
  • Preparation for rebar installation in existing dressing rooms.
  • Installing block walls in Aquatic Centre
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available.

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.


If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here.


𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

  • Sheathing curtain wall & installing parapets on Arena extension.
  •  Installation of mechanical underground piping in Arena extension.
  • Back filling and subgrade preparation for concrete slab in existing Arena dressing rooms.
  • Installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre.
  • Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre.
  • Opening new access/pathway to the Daycare from Bonhomme Street.

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

  • Back filling & subgrade preparation in Arena extension.
  • Installing parapets on Arena extension.
  • Ongoing subgrade preparation for concrete slab in existing Arena dressing rooms.
  • Ongoing installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre.
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available.

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.


The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

𝐇𝐞𝐫𝐞’𝐬 𝐰𝐡𝐚𝐭 𝐡𝐚𝐩𝐩𝐞𝐧𝐞𝐝 𝐭𝐡𝐢𝐬 𝐰𝐞𝐞𝐤:

▪ Ongoing curtain wall & parapet framing on Arena extension. 

▪ Installation of mechanical underground piping in Arena extension. 

▪ Subgrade preparation for concrete slab in existing Arena dressing rooms. 

▪ Installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre.

▪ Installation of mechanical and electrical ceiling rough-ins in Aquatic Centre.

▪ Placement and finishing of concrete infills in Activity Centre. 

𝐏𝐥𝐚𝐧𝐬 𝐟𝐨𝐫 𝐧𝐞𝐱𝐭 𝐰𝐞𝐞𝐤:

▪ Ongoing installation of mechanical underground piping in Arena extension. 

▪ Ongoing curtain wall installation on Arena extension. 

▪ Ongoing subgrade preparation for concrete slab in existing Arena dressing rooms. 

▪ Ongoing installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre. 

▪ Installation of mechanical and electric ceiling rough-ins in Aquatic Centre. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service 

Here’s what happened this week:

  • Ongoing curtain wall & parapet framing on Arena extension 
  • Installation of mechanical underground piping in Arena extension 
  • Subgrade preparation for concrete slab in existing Arena dressing rooms 
  • Installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre 
  • Preparation of concrete infills in Activity Centre  

Plans for next week: 

  • Ongoing curtain wall installation on Arena extension 
  • Ongoing installation of mechanical underground piping in Arena extension 
  • Ongoing subgrade preparation for concrete slab in existing Arena dressing rooms 
  • Ongoing installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre 
  • Installation of mechanical and electric ceiling rough-ins in Aquatic Centre
  • Completion of concrete infills in Activity Centre 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Curtain wall & parapet framing on Arena extension 
  • Installation of fall arrest (a system used to prevent an employee in a fall from a working level) for Arena extension 
  • Ground thawing in Arena extension to prepare for underground mechanical rough-ins
  • Layout & electrical relocates in Aquatic Centre 
  • Preparation work for concrete infills in Activity Centre 
  • Preparation work for Wildflowers Daycare access from Bonhomme Street 

Plans for next week: 

  • Ongoing curtain wall & parapet framing on Arena extension 
  • Installation of mechanical underground piping in Arena extension 
  • Subgrade preparation for concrete slab in existing Arena dressing rooms 
  • Installation of fire rated ceilings and miscellaneous framing work in Aquatic Centre 
  • Completion of concrete infills in Activity Centre 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 


 

Construction crews returned from their holiday break the morning of Tuesday, January 2nd.  

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 of 2024 as anticipated.  

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

 Here’s what happened this week: 

  • Concrete slab poured & saw cutting in Aquatic Centre changerooms 
  • Heating lines relocated in Aquatic Centre 
  • Preparation work for parapets (a barrier that is an upward extension of a wall at the edge of a roof) on Arena extension. 

Plans for next week:  

  • Curtain wall & parapet framing on Arena extension 
  • Installation of fall arrest (a system used to prevent an employee in a fall from a working level) for Arena extension 
  • Ground thawing in Arena extension to prepare for underground mechanical rough-ins
  • Layout & electrical relocates in Aquatic Centre 
  • Preparation work for concrete infills in Activity Centre 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 

 

 

 

Construction crews will be taking a holiday break next week. Work will conclude around 12:00 noon on Saturday, December 23 and resume the morning of Tuesday, January 2. Weekly updates will resume Friday, January 5. 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 0f 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Preparation for Q-deck (composite metal flooring) installation in existing Arena dressing rooms. 
  • Rebar installation in Aquatic Centre changerooms. 
  • Installation of waterproofing in elevator pit. 
  • Installation of concrete in elevator pit. 
  • Plumbing rough-in Activity Centre elevator and change room areas (basement).
  • Removal of material and concrete from Activity Centre basement.

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 


 

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 0f 2024 as anticipated.

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Ongoing structural steel installation for Arena extension. 
  • Aquatic Centre slab-on-grade (concrete installation) work. 
  • Subgrade preparation in existing Arena dressing rooms. 
  • Removal of materials and concrete in Activity Centre basement. 
  • Plumbing rough-in for Activity Centre basement. 
  • ATCO natural gas installation.
     

Plans for next week: 

  • Preparation for Q-deck (composite metal flooring) installation in existing Arena dressing rooms. 
  • Rebar installation in Aquatic Centre changerooms. 
  • Installation of waterproofing in elevator pit. 
  • Installation of concrete in elevator pit. 
  • Plumbing rough-in for Activity Centre basement. 


Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

Timelines are tentative and are subject to change depending on unforeseen circumstances that occur during construction.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 

 

The Jasper Recreation Facilities Renovation Project continues to be on track to finish within budget in Q3 0f 2024 as anticipated.

The staged re-opening of the Aquatic Centre will not start in Q1 of 2024 as anticipated. Previously unknown site conditions that required extensive hazardous materials removal, and significant re-design have affected the Aquatic Centre construction timeline. The Aquatic Centre is now anticipated to open in mid-Q 2 of 2024. We know that residents are eager to get back into the Aquatic Centre, and we apologize for this unanticipated extended closure.

The Activity Centre basement and upper Curling Lounge will not re-open in Q2 of 2024 as anticipated due to site conditions related to the elevator placement and existing building structure constraints. The anticipated competition date for these areas has been extended to Q3. 

If you have questions or concerns regarding the Jasper Recreation Facilities Renovation Project, please fill out a feedback form on our website here: www.jasper-alberta.ca/p/e-service

Here’s what happened this week:

  • Structural steel installation for Arena extension. 
  • Subgrade preparation in Aquatic Centre. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 
  • Construction crews were able to complete some of the steel installation work for the Arena extension earlier than anticipated, and Bonhomme Street was able to re-open Thursday evening to two-way traffic. 

Plans for next week:

  • Ongoing structural steel installation for Arena extension. 
  • Aquatic Centre slab-on-grade (concrete installation) work. 
  • Subgrade preparation in existing Arena dressing rooms. 
  • Removal of materials and concrete in Activity Centre basement. 
  • Plumbing rough-in for Activity Centre basement. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

 

 

 

Beginning Sunday, December 3rd, Bonhomme Street will be closed in front of the Jasper Activity Centre & Arena and Our Lady of Lourdes Catholic Church. 

The sidewalk on Bonhomme Street from Elm Street to the Fitness & Aquatic Centre, Museum, Catholic Church, and the parking lot/ recycling depot will remain open during the closure, as well as access from the parking lot to the Fitness & Aquatic Centre. Detour signage will be posted in the area, and the main parking lot and recycling centre will be accessible via the West entrance/exit.

This closure is necessary to accommodate steel installation work, and is anticipated to last until December 16th

There will be a separate post on social media, and our website regarding this closure. 

Here’s what happened this week:

  • Exterior Arena extension block walls completed, and temporary hoarding removed. 
  • Demolition of portion of canopy roof for new Arena extension & installation of temporary shoring. 
  • Subgrade preparation in Arena and Aquatic Centre. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 
  • Installation of exterior stairs for roof access.
  • Site preparation for Arena steel installation. 

Plans for next week:

  • Structural steel delivery & installation, and road closure on Bonhomme Street. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 
  • Subgrade preparation in Arena and Aquatic Centre. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 


Here’s what happened this week:

  • Formwork and concrete pouring for elevator pit and walls. 
  • Demolition of portion of canopy roof for new Arena extension. 
  • Ongoing installation of exterior block wall for new Arena extension. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 

Plans for next week: 

  • Site preparation for Arena steel installation. 
  • Installation of temporary shoring for Arena canopy. 
  • Backfilling elevator pit & piping tie-ins. 
  • Subgrade preparation in Arena and Aquatic Centre. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 


Here’s what happened this week:

  • Ongoing excavation in Activity Centre to accommodate elevator. 
  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing installation of exterior block wall for new Arena extension. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 

Plans for next week:

  • Starting formwork and pouring concrete for elevator slab and walls. 
  • Ongoing installation of exterior block wall for new Arena extension. 
  • Ongoing Demolition of portion of canopy roof to accommodate Arena extension. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project. 

 

Here’s what happened this week:

  • Ongoing excavation in Activity Centre to accommodate elevator. 
  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing concrete slab removal in the Aquatic Centre changerooms. 
  • Started exterior block wall for new Arena extension. 
  • Started underground plumbing in existing Arena dressing rooms and Aquatic Centre. 

 

Plans for next week: 

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing concrete slab removal in the Aquatic Centre changerooms. 
  • Ongoing excavation in Activity Centre to accommodate elevator. 
  • Installing exterior block wall for new Arena extension. 
  • Demolition of portion of canopy roof to accommodate Arena extension. 
  • Ongoing underground plumbing in existing Arena dressing rooms and Aquatic Centre. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available.  

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project. 

 

 

Stop signs have been installed on the Pyramid Lake Road crosswalk, directly beside the temporary dressing rooms. Motorists and pedestrians are asked to take extra caution in this area due to reduced visibility. 

Here’s what happened this week: 

  • Ongoing excavation in Activity Centre to accommodate elevator. *construction crews are finding lot’s of large boulders, see photo below*
  • Completion of steel installation for new dressing rooms in existing Arena. 
  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing concrete slab removal in the Aquatic Centre changerooms. 
  • Backfilling around exterior foundation walls and grade beam.  

Plans for next week:

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing concrete slab removal in the Aquatic Centre changerooms. 
  • Ongoing excavation in Activity Centre to accommodate elevator. 
  • Start exterior block wall for new Arena extension. 
  • Demolition of portion of canopy roof to accommodate Arena extension. 
  • Start underground plumbing in existing Arena dressing rooms and Aquatic Centre.

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase

Thank you for your continued patience as we navigate the renovation project. 

 

The temporary external Arena dressing rooms arrived in Jasper today. These temporary dressing rooms are two 60-foot modular buildings, and will have two 12 foot by 30 foot rooms in each, for a total of four temporary dressing rooms. These modular buildings have been placed beside the Arena on Pyramid Lake Road. 

Tourism Jasper and the Municipality of Jasper will be completing the required permitting, and other requirements to make these temporary dressing rooms operational over the coming weeks, and ready for tournaments and league games in December. 

We look forward to having this increased level of service during the renovation project, and we would like to thank Tourism Jasper for their efforts in making this a possibility. 

Here’s what happened this week: 

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Completion of damp proofing & insulation of exterior foundation walls.
  • Installation of steel for new dressing rooms in existing Arena. 
  • Concrete slab removal in Activity Centre basement and main floor to accommodate elevator. 

Plans for next week:

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing concrete slab removal in the Aquatic Centre changerooms. 
  • Ongoing excavation in Activity Centre to accommodate elevator. 
  • Backfilling around exterior foundation walls and grade beam. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 

Thank you for your continued patience as we navigate the renovation project.    


With recreation activities returning to the Jasper Activity Centre, there has been an increase in traffic in the Commemoration Park parking lot. 

To make the parking lot safer and more accessible for community members accessing the facility daily, we are making some changes to the parking time limits in this lot.  

The parking stalls directly next to the Activity Centre in the Commemoration Park parking lot will become 15-minute only parking. Signage will be put up in the coming weeks and this will be enforced during peak times.   

We want to take this opportunity to remind everyone that there is access to the Jasper Arena from Pyramid Lake Rd, and the parking lot on Bonhomme Street on the other side of the Recreation Facility is available for longer term parking.

Here’s what happened this week:

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Ongoing Arena foundation work – pouring concrete walls. 
  • Ongoing formwork for Arena extension. 
  • Concrete slab removal in Activity Centre basement and main floor to accommodate elevator. 

Plans for next week: 

  • Ongoing demolition in Aquatic Centre, Activity Centre, and Curling Lounge. 
  • Concrete slab removal in the Aquatic Centre. 
  • Excavation in Activity Centre to accommodate elevator. 
  • Installation of steel for new dressing rooms in existing Arena. 
  • Damp proofing & insulation of exterior foundation walls. 

 

Activity Centre users can expect some construction noise. Fitness Centre users can expect construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

Thank you for your continued patience as we navigate the renovation project.    

 

 

A 15-minute loading zone is now in effect on Pyramid Lake Road beside the Activity Centre and Arena with signage in place. To access the arena, please use the doors on Pyramid Lake Road. 

Here’s what happened this week:

  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing abatement work in Aquatic Centre.
  • Ongoing demolition in the Arena. 
  • Ongoing Arena foundation work – pouring concrete walls. 
  • Shoring installed in existing change rooms for removal of structural columns. 
  • Ongoing abatement work in the Curling Lounge. 
  • Ongoing demolition in the Curling Lounge. 

Plans for next week:

  • Ongoing abatement work in the Curling Lounge. 
  • Ongoing demolition in Aquatic Centre, Arena, and Curling Lounge. 
  • Concrete slab removal in Activity Centre basement and main floor to accommodate elevator. 
  • Ongoing arena foundation work – pouring concrete footings. 

Activity Centre users can expect some construction noise. Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

Pete and the Arena team have been busy putting the ice in and painting the lines over the last week, and the ice will be ready tomorrow. An ice users group meeting was held on Tuesday, and we will update the Arena schedule in the coming weeks. 

Here’s what happened this week:

  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing abatement work in Aquatic Centre.
  • Ongoing demolition in the Arena. 
  • Arena foundation – forming and concrete placement.
  • Abatement work in the Curling Lounge. 
  • Demolition in the Curling Lounge. 

Plans for next week:

  • Ongoing abatement work in the Curling Lounge. 
  • Ongoing demolition in Aquatic Centre, Arena, and Curling Lounge. 
  • Concrete slab removal in Activity Centre basement and main floor to accommodate elevator. 
  • Ongoing Arena foundation – pouring concrete walls. 


Activity Centre users can expect some construction noise. Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

Construction crews were able to complete the abatement work in the Jasper Activity Centre basement, and Out of School Care was able to move back into their regular spaces on Thursday afternoon. 

Here’s what happened this week:

  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing abatement work in Aquatic Centre. 
  • Ongoing concrete slab removal in Arena dressing rooms. 
  • Excavation for Arena extension footings.
  • Arena foundation – forming and concrete placement.
  • Completion of abatement work in the Jasper Activity Centre basement. 
  • Installation of temporary walls in Gymnastics and Wildflowers Childcare Centre.
  • Installation of temporary hoarding walls in Activity Centre basement.
  • Installation of temporary hoarding walls in the Arena. 
  • Completion of elevator installation layout. 


Plans for next week:

  • Abatement work in the curling lounge. 
  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing abatement work in Aquatic Centre. 
  • Ongoing Arena foundation – forming and concrete placement.

Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.


Construction crews were able to complete the Aquatic Centre waterline installation earlier than anticipated, and the detour on Bonhomme Street resumed to two-way traffic on Saturday, September 16th

Here’s what happened this week:

  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing abatement work in the Aquatic Centre. 
  • Ongoing concrete slab removal in Arena dressing rooms. 
  • Excavation for Arena extension footings.
  • Arena foundation – forming and concrete placement 
  • Ongoing abatement work in the Jasper Activity Centre basement. 
  • Completion of waterline to the Aquatic Centre. 

Plans for next week:

  • Ongoing demolition of Aquatic Centre changerooms. 
  • Ongoing abatement work in Aquatic Centre. 
  • Ongoing excavation for Arena extension footings. 
  • Ongoing Arena foundation – forming and concrete placement 
  • Ongoing abatement work in Activity Centre basement – expected to be completed September 25th 
  • Installation of temporary walls in Gymnastics and Wildflowers Childcare Centre 
  • Installation of temporary hoarding walls in Activity Centre basement 
  • Elevator installation layout. 

Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

 

 

 

The detour on Bonhomme Street has been extended to September 22nd to accommodate the removal of a concrete utility vault, and installation of site services to the Fitness & Aquatic Centre.

A water shutdown will be necessary on Saturday, September 16th, and the Jasper Activity Centre will be open starting at 1:00pm. All affected residents and businesses in the area have been notified. 

Here’s what happened this week:

  • Ongoing installation of waterline to the Fitness & Aquatic Centre. 
  • Ongoing demolition in Aquatic Centre changerooms. 
  • Ongoing concrete slab removal in Arena dressing rooms. 
  • Excavation for Arena extension footings.
  • Abatement work in the Jasper Activity Centre basement.  

Plans for next week: 

  • Ongoing demolition of concrete slab removal in arena. 
  • Ongoing demolition of Aquatic Centre changerooms. 
  • Ongoing abatement work in Jasper Activity Centre basement.
  • Abatement work in the Aquatic Centre. 
  • Concrete formwork for Arena extension. 
  • Ongoing installation of waterline to the Fitness & Aquatic Centre. 

 

Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

On Tuesday, September 5th, the Aquatic Centre closed for approximately four months. The closure will facilitate the Jasper Recreation Facilities Renovation Project, as well as our usual shutdown procedures. 

Here’s what happened this week:

  • Ongoing installation of site services to the Fitness & Aquatic Centre. 
  • Beginning stages of demolition in Aquatic Centre changerooms. 
  • Concrete slab removal in arena. 
  • Road Closure on Bonhomme Street with traffic detouring through the parking lot. This closure is expected to end September 18th

Plans for next week: 

  • Ongoing demolition of concrete slab removal in arena. 
  • Ongoing demolition of Aquatic Centre changerooms. 
  • Ongoing installation of site services to the Fitness & Aquatic Centre. 

Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms are available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

Starting Tuesday, September 5th, Bonhomme Street will be closed and traffic will be detoured through the Jasper Activity Centre parking lot. Motorists are asked to follow detour signage, drive slowly, and remain diligent when driving through the detour. This closure is required in order for construction crews to complete site services to the Fitness & Aquatic Centre, and is expected to last until September 15th

Also starting Tuesday, September 5th, the Aquatic Centre will be closed for approximately four months. The closure will facilitate the Jasper Recreation Facilities Renovation Project, as well as our usual shutdown procedures. 

Here’s what happened this week:

  • Re-opening of Bonhomme Street to two-way traffic. 
  • Ongoing demolition of cinderblock walls in Arena dressing rooms. 
  • Demolition of old ammonia & mechanical room. 
  • Demolition of the Jasper Activity Centre reception desk. 
  • Ongoing abatement work in the Jasper Activity Centre ceiling. 
  • Installation of window in Wildflowers Childcare temporary access door.  

Plans for next week:

  • Ongoing demolition of concrete slabs in Arena dressing rooms. 
  • Beginning stages of demolition in Fitness & Aquatic Centre changerooms. 
  • Installation of site services to the Fitness & Aquatic Centre. 
  • Ongoing demolition and abatement work in the Jasper Activity Centre. 
  • Road Closure on Bonhomme Street with traffic detouring through the parking lot.

Fitness Centre users can expect loud construction noise, and no access to changerooms. Temporary washrooms will be available. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

As of Friday afternoon, Bonhomme Street has re-opened to two-way traffic. A large portion of the road closest to the Jasper Activity Centre and Fitness & Aquatic Centre will remain blocked off in order for Carlson Construction to continue working on underground site services. Vehicles cannot park on either side Bonhomme Street in front of the Jasper Activity Centre/ Fitness & Aquatic Centre/Catholic Church, please park in the parking lot. ‘No parking’ signage is in place.

Here’s what happened this week:

  • Ongoing demolition of cinderblock walls in Arena dressing rooms. 
  • Abatement work in the Jasper Activity Centre ceiling. 
  • Demolition of concrete in courtyard/main entrance. 
  • Ongoing installation of site services including waterlines and stormwater lines. 
  • Preparation for re-opening of Bonhomme Street to two-way traffic. 

Plans for next week:

  • Ongoing demolition in Arena dressing rooms. 
  • Preparation for concrete slab removal work in Arena dressing rooms. 
  • Ongoing abatement working throughout the facility. This work poses no risk to the public.

Visitors to the Activity Centre can expect to see workers in protective clothing while abatement work is being conducted, as this is required by the Alberta Occupational Health & Safety Legislation when working with hazardous materials. Englobe will be checking the air quality on a regular basis when this work is happening.  

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.



It was another busy week for the Jasper Recreational Facilities Renovation Project with abatement work completed in the Arena dressing rooms. 

Here’s what happened this week:

  • Sanitary sewer line installed for the new Arena extension.
  • Installation of stormwater line in the Courtyard between the Arena and Fitness & Aquatic Centre.
  • Completed the demolition of the Jasper Activity Centre canopy at the entrance. 
  • Started demolition in the curling lounge. 
  • Abatement work completed in Arena dressing rooms.
  • Demolition of cinderblock walls in Arena dressing rooms.  

Plans for next week: 

  • Ongoing installation of site services including waterlines and stormwater lines. 
  • Ongoing demolition of cinderblock walls in Arena dressing rooms. 
  • Abatement work in the Jasper Activity Centre ceiling. This work poses no risk to the public.
  • Preparing for opening of Bonhomme Street to 2-way traffic.  

Visitors to the Activity Centre can expect to see workers in protective clothing while abatement work is being conducted, as this is required by the Alberta Occupational Health & Safety Legislation when working with hazardous materials. Englobe will be checking the air quality on a regular basis when this work is happening. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase. 


It was another busy week for the Jasper Recreational Facilities Renovation Project with the ongoing installation of site services including waterlines and stormwater lines. 

 Here’s what happened this week:

  • Ongoing demolition of dressing rooms and other areas. 
  • Abatement preparation work.  

Plans for next week:

  • Low risk asbestos abatement work.  
  • Ongoing demolition work. 
  • Ongoing installation of site services. 

Starting Tuesday, August 15th, low-risk hazardous material (vermiculite) removal work will be taking place on the south exterior wall. This work poses no risk to the public.
Visitors to the Activity Centre and Wildflowers Childcare can expect to see workers in protective clothing while this work is being conducted, as this is required by the Alberta Occupational Health & Safety Legislation when working with hazardous materials. Englobe will be checking the air quality on a regular basis when this work is happening.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

 

It was another busy week for the Jasper Recreational Facilities Renovation Project, starting with Bonhomme Street being closed in front of the Jasper Activity Centre to allow construction crews to install underground services including water and sewer lines. Carlson construction has stated that work is on schedule, and still anticipate for this closure to remain in effect until August 18th.  

Here’s what else happened this week:

  • Ongoing demolition of arena dressing rooms. 
  • Started asbestos abatement work which includes a set of procedures specifically designed to control the release of asbestos fibers from asbestos-containing materials that are located in the Jasper Activity Centre. 
  • Disconnection of mechanical and electrical in demolition areas. 
  • Installation of temporary walls in the arena.  

Plans for next week: 

Construction will shut down for the long weekend, and crews will be back on-site Tuesday morning.  

  • Ongoing installation of site services, including waterlines and stormwater lines. 
  • Ongoing demolition of dressing rooms and other areas. 

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

It was a busy week for the Jasper Recreation Facilities Renovation Project, and significant changes are now visible at the Jasper Activity Centre and the Arena. 

 Here’s what happened this week:

  • Electricians were on-site disconnecting any electrical required for demolition, and reviewing the site for upcoming electrical work that will be required. 
  • Demolition subcontractors removed two exterior canopies on the arena, and the reception desk. 
  • Removal of all concrete sidewalks and asphalt in the fenced off area.
  • Survey layout conducted to determine location of site services and new foundations. 
  • Private locates determined where underground utility lines are located. 
  • Beginning stages of site services installation: water supply and distribution services, and sanitary sewer collection. 
  • Ice plant testing. 

Plans for next week:

  • Ongoing demolition of arena dressing rooms. 
  • Starting asbestos abatement work which includes a set of procedures specifically designed to control the release of asbestos fibers from asbestos-containing materials that are located in the Jasper Activity Centre. 
  • Underground site services installation: water supply and distribution services, and sanitary sewer collection. Bonhomme Street in front of the Jasper Activity Centre will be closed from July 31 until approximately August 18 to complete this work. Click here for more information. 
  • Disconnection of mechanical and electrical in demolition areas. 
  • Installation of temporary walls in the arena. These walls are called “hoarding walls” and are installed around a construction site while construction is going on and is then taken down once the work is finished.

We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 

Carlson Construction crews were on-site early Monday morning, kicking off the Jasper Recreation Facilities Renovation project. 

Here’s what happened this week:

  • Bonhomme Street entrance/exit was closed and fenced off, and a temporary entrance/exit is at the Commemoration Park doors. 
  • Wildflowers Childcare received a new, temporary entrance to ensure safe access throughout construction.
  • Diggers were on-site, and all of the old rubber mats and general main entrance area has been removed.
  • The new ice plant received sod, making this part of the renovation complete.

Plans for next week:

  • Electricians will be on-site disconnecting any electrical required for demolition, and to review the site for upcoming electrical work that will be required. 
  • Demolition subcontractors will  be on-site, removing two exterior canopies on the arena, and the reception desk. 
  • Finish the removal of all concrete sidewalks and asphalt in the fenced off area.
  • Survey layout will be conducted to determine location of site services and new foundations. 
  • Private locates will determine where underground utility lines are located. 
  • Starting the installation of site services: water supply and distribution services, and sanitary sewer collection. 
  • Ice plant testing. 

Residents in the area and visitors at the Jasper Activity Centre can expect lots of construction activity, which will be loud at times. 

We anticipate that next weeks update will provide a construction schedule for the next few months. 

 We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.

 


We’re excited to announce that construction for the Jasper Recreation Facilities Renovation Project will begin starting on Monday, July 17th

The project will enter a significant milestone as the contractor, Carlson Construction, will begin demolition work, marking an important step towards revitalizing the Activity Centre, Arena, and Fitness & Aquatic Centre facilities. 

Starting Monday, July 17th the Bonhomme Street entrance/exit (west) will be closed to ensure the safety of residents, staff, and workers in the area.  

  • Parents, guests, and users of these facilities are kindly requested to use the Commemoration Park (east) entrance/exit to ensure continued access to the Activity Centre and Wildflowers Childcare facility. Signage and guidance will be in place to assist with the new access route, ensuring a smooth transition for all users.  
  • The Activity Centre Front Desk has been relocated to the old registry office, and signs are in place.   
  • Glenda’s Concession will remain open throughout the construction phase. 
  • East parking lot (Commemoration Park) : 
    • Municipal staff have been asked to park in the large parking lot on Bonhomme, or on the street.
    • Additional bike racks have been installed to ensure we have adequate space for those that are biking. 
    • We would like to remind people to stay safe and vigilant in the parking lot due to the increase in usage. 

The full closure of the Bonhomme Street (west) entrance/exit is necessary to facilitate the demolition process and prepare the site for the exciting improvements to come. We expect the closure to be in place from July to November.
We apologize for any inconvenience caused and appreciate the community's understanding during this phase.

In the coming weeks, we anticipate we will be able to provide a construction schedule for the next few months. We are and will continue to actively work on prioritizing access for local youth, maintaining safety, and engagement with stakeholders throughout the construction phase.